McDermott has won an engineering, procurement, construction and installation (EPCI) contract from Qatargas for expansion of the North Field offshore facilities in the State of Qatar.
The contract for new facilities includes the full suite of EPCI services for eight new offshore jackets.
McDermott plans to use its project management and engineering teams in Doha, Qatar, with fabrication primarily taking place at McDermott’s facilities in Batam, Indonesia.
Vessels Derrick Barge 50 and Derrick Barge 27 from McDermott’s fleet are scheduled to undertake the installation and completions work.
The work is expected to begin immediately and will be booked into McDermott’s second quarter 2019 backlog.
The contract is said to be between USD $50 million and USD $250 million.